Pelham Drive Lift Station and Central Regional Lift Station

This project consisted of improvements to the Pelham Drive Lift Station and Central Regional Lift Station in Sedalia, MO.

This project consisted of improvements to the Pelham Drive Lift Station and Central Regional Lift Station in Sedalia, MO.


At the Pelham Drive Lift Station, Infrastructure Solutions was responsible for the construction of a new six-foot Dia. valve vault, eight-foot Dia. wet well, two (2) 40 HP pumps, pump controls, generator, davit crane, site restoration, and all associated appurtenances.


At the Central Regional Lift Station, Infrastructure Solutions was responsible for the construction of a new 10-foot Dia. value vault, 10-foot Dia. wet well, two (2) 25 HP pumps, pump controls, generator, davit crane, site restoration, gravel drive. approximately 2,350 linear feet of gravity sewer, approximately 4,800 linear feet of force main, and all associated appurtenances.